REPORT OF THE AUDITOR.GENERAL ON CITY OF KISUMU FOR THE YEAR ENDED 30 JUNE, 2024

 


UNSUPPORTED STAFF COST

The statement of financial performance reflects an amount of Kshs.238,422,534 in respect of staff cost. 

However, the expenditure relates to payments of salaries for both staff of the County Executive of Kisumu and the City of Kisumu and therefore it was not possible to confirm the staff cost expenditure that relate to the City of Kisumu.

In the circumstances, the accuracy and completeness of the reported staff cost of

Kshs.238,422,534 could not be confirmed.

VARIANCES UNDER TRANSFER FROM THE COUNTY GOVERNMENT

The statement of financial performance reflects an amount of Kshs.402,159,385 in respect of transfers from the County Government. 

However, the Kisumu County Executive financial statement reflect an amount of Kshs.422,908,693 resulting to unexplained and unreconciled variance of Kshs.20,749,308. 

Further, the financial statement reflects an amount of  Kshs.426,594,893 in respect of transfers from the County Government resulting to unexplained and unreconciled variance of Kshs.24,436.

In the circumstances, the accuracy and validity of the transfers from the County Government of Kisumu of Kshs.402,159,385 for the year ended 30 June, 2024 could not be confirmed.

UNSUPPORTED PROPERTY, PLANT AND EQUIPMENT

The statement of financial position reflects property, plant and equipment balance of

Kshs.432,608,059 which includes additions for the year amounting to Kshs.136,77O,854.

However, during the audit, two (2) payment vouchers amounting to Kshs.29,040,000 were not availed for audit. 

The propriety of the expenditure of Kshs.29,040,000 could therefore not be ascertained. 

Further, Management has not supported the transfers /adjustments of Kshs.305,040,557 under work in progress and evidence of valuation was not provided.

CONSTRUCTION OF THE NON-MOTORIZED TRANSPORT SYSTEM PHASE 2

Management signed a contract on 4 August, 2020 for the construction of a non-motorized transport system phase 2 at a contract sum of Kshs.659,065,834, and an implementation period of twenty-four (24) months and expected completion date of 3 August, 2022.

During the year under review, a physical inspection of the project during the Month of November, 2024 revealed that the project is still at 75% level of completion and the balance of Kshs.43,942,189.77 has not yet been paid by the County Executive.

Management has explained that they have revised the contract sum to Kshs.513,796,700 through an addendum and actively prioritizing the packaging and implementation of the descoped works under the next KUSP phase to ensure full completion.

IMPROVEMENT OF JOMO KENYATTA SPORTS GROUND

Management signed a contract on 14 August, 2020 for the improvement of Jomo Kenyatta sports ground at a contract sum of Kshs.111,328,291 and an implementation period of twenty-four (24) months and expected completion date of 13 August, 2022.

The final contract sum at handing over was revised to Kshs.93,832,288. 

The amount paid to date for the revised scope is Kshs.56,739,433 with a balance of Kshs.37,092,855.65 committed to be paid by the county executive in the next financial year. 

However, there is no evidence that the World Bank will finance Phase ll of the project and no explanation as to why the project was not completed in time was given.

CONSTRUCTION OF NYAMASARIA BUS PARK

Management signed a contract on 4 August, 2020 for the construction of Nyamasaria Bus Park at a contract sum of Kshs.99,883,902. 

The implementation period was twenty-four (24) months and expected completion date of 3 August, 2022.

The projected final account at handing over was revised to Kshs.'104,400,481. 

The amount paid to date for the certified works is Kshs.65,253,146 with a pending certificate of Kshs.16,605,870.22 and uncertified amount of Kshs. 22,541,465 committed to be paid by the county executive in the next financial year. 

No explanation has been given for revised amount and for the delay in the completion of the work.

In the circumstances, the value for money received from the public funds spent on construction of the projects during the year under review could not be confirmed and Management was in breach of the law.

ENGAGEMENT OF LEGAL SERVICES WITHOUT APPROVAL

Review of records provided for legal fees together with the supporting documentation revealed that Management entered into contracts with advocates for provision of consultancy services for various cases and were paid Kshs.1,997,520. 

However, no approval was granted by the County Executive Committee member to engage the services of a consultant for the provision of legal services

Comments

Popular posts from this blog

Parking Commander Vincent Tom Mboya at City Hall Accused of Eloping with Colleague's Spouse

Controversy Erupts as Reports Allege Parking Deputy Commander Vincent Mboya Caught in Relationship With Colleague’s Spouse

CBD Traders Laud Chief Officer Security and Compliance Madam Eva for Smooth Holiday Operations